The Dismantling Phases - DELPHI/LHCb EXPO |
The planning below has been established under the assumption that the DELPHI/LHCb EXPO project will be realized. It foresees to keep the Barrel (after the outer MUB chambers have been shaved off) in the UX85 caverns. The endcaps are completely dismantled. The barracks D1, D2, B2 and A3 are left in the cavern for reuse by LHCb. The dates are given in weeks after the To date.
This representation is only meant to give an overview of the dismantling sequence. Consult the detailed planning (MS Project or Task list) for details and dates.
(status 22 Nov 2000)
Phase Iweek 1
purge flam. gases demagnetize solenoid preparatory tasks |
|
Phase IIweek 2 - 4
open endcaps warm up solenoid dismantle * Beampipe * MUB periph. chambers
|
|
Phase IIIweek 5 - 8
endcaps in garage position dismantle * RIF * FCB * FEMC * MUB outer chambers * Platf. B4 + Bar. B3
|
|
Phase IVweek 9 - 12
|
|
Phase Vweek 13 - 17
dismantle * FHAC thin endcap * FHAC thick endcap |
|
Phase VIweek 18 - 20
dismantle * Platf. A3 + C3 * Bar. C2 + C1
|
|
Phase VIIweek 21 - 24
dismantle * Platf. D3 * Install B2 + A3 on top
|
C.Joram 30/08/2001