(A.Augustinus, Ph.Gavillet-CERN/EP - 22nd Dec.
2000)
Schedule
| 2 0 0 0 | | 2 0 0 1
Week: |--48--|--49--|--50--|--51--|......|-- 2--|-- 3--|-- 4--|-- 5--|-- 6--|
Dates |27 01|04 08|11 15|18 22| |08 12|15 19|22 26|29 02|05 09|
--------|------|------|------|------|------|------|------|------|------|------|
Central |DAS+SC| ID |
Detector|FCA | HPC |BRICH | |..FEMC, MUF ->
|FCB | TPC (B2 + D2) |
|STIC | OD |VD |
|MUB | TOF |HACMUS|
Comments
- Most of the Central and Detector Electronics has been dismantled, properly packed on
palettes and stored in the SU8 (2880) building.
- An exhaustive inventory of EP-Pool electronics has been completed in collaboration with
the EP-Pool responsibles. The actual lists can be found at EP-Pool lists.
- Although no final storage space could yet be found by the EP Pool, the rental has been
canceled.
Next year
- Removal of detectors:
- Only the dismantling of the EMF and MUF electronics in A2, C2 is left. It is scheduled
to occur early january.
- Recuperation of absolete electronics
- All requests have been registered. Please send urgently yours, if not already done.
- We'll try to satisfy all of them i.e we'll prepare the stuff which could be exported for
free.
- On the other hand, requesters are reminded that:
- All equipment on loan from the EP-Pool has to be returned except if DELPHI property (i.e
bought on common orders) or classified in the "cancel" category.
- All equipment on a CERN inventory has to be registered as canceled.
- Shipping request has to be filled up for recuperated equipment to be exported.
Many thanks for the efficient support to:
- The two electro-technicians from LHCb
- The detector teams
- ... and obviously the DELPHI crew