Project Start Date: Mon 6/11/00
Project Finish Date: Fri 25/5/01
ID | Task_Name | Duration | Start_Date | Finish_Date |
---|---|---|---|---|
1 | Réaménagement UX 85 |
20 days | Mon 25/9/00 | Fri 20/10/00 |
2 | Réaménagement SX 8 - Réduction de l'emprise ATELIER Démontage de l'expo DELPHI |
20 days | Mon 9/10/00 | Fri 3/11/00 |
3 | remove central electronics |
10 days | Mon 27/11/00 | Fri 8/12/00 |
4 | remove electronics B3, B2, B1 |
20 days | Mon 11/12/00 | Fri 19/1/01 |
5 | remove electronics B3, B2, B1 |
20 days | Mon 11/12/00 | Fri 19/1/01 |
6 | remove electronics C2, C1 |
50 days | Mon 11/12/00 | Fri 2/3/01 |
7 | remove electronics A2, A1 |
50 days | Mon 11/12/00 | Fri 2/3/01 |
8 | remove electronics D2, D1 |
50 days | Mon 11/12/00 | Fri 2/3/01 |
9 | Prepare platform B4 |
20 days | Mon 11/12/00 | Fri 19/1/01 |
10 | Prepare platform C3, A3 |
50 days | Mon 11/12/00 | Fri 2/3/01 |
11 | Prepare platform D3 |
45 days | Mon 18/12/00 | Fri 2/3/01 |
12 | Phase I |
20 days | Mon 6/11/00 | Fri 1/12/00 |
13 | GAZ / Détecteurs - Purge |
15 days | Mon 6/11/00 | Fri 24/11/00 |
14 | Bouchon PX / Gaine d'extraction |
5 days | Mon 27/11/00 | Fri 1/12/00 |
15 | VSAT+Câblage STIC Système de ventil.intérieur BARREL |
2 days | Thu 23/11/00 | Fri 24/11/00 |
16 | SMC 4 ch sup + 4 ch inf |
2 days | Thu 23/11/00 | Fri 24/11/00 |
17 | Arrêt du solénoïde |
1 day | Mon 6/11/00 | Mon 6/11/00 |
18 | SOLENOÏDE - Démagnétisation |
5 days | Mon 13/11/00 | Fri 17/11/00 |
19 | Phase II |
25 days | Mon 20/11/00 | Fri 22/12/00 |
20 | SOLENOÏDE - réchauffement |
5 days | Mon 20/11/00 | Fri 24/11/00 |
21 | Solénoïde / N2 |
1 day | Fri 24/11/00 | Fri 24/11/00 |
22 | open blindage / endcaps |
1 day | Mon 20/11/00 | Mon 20/11/00 |
23 | Vidange circuits EM-EG-EDem- |
2 days | Mon 27/11/00 | Tue 28/11/00 |
24 | Dépose tuyauteries EM-EG-EDem / B4-D3 |
3 days | Wed 29/11/00 | Fri 1/12/00 |
25 | Dépose des pompes à vide |
3 days | Tue 5/12/00 | Thu 7/12/00 |
26 | Chambres,câbles + équipements He |
5 days | Mon 4/12/00 | Fri 8/12/00 |
27 | Cannes CRYO-D3 (check with Klaus Barth) |
2 days | Mon 4/12/00 | Tue 5/12/00 |
28 | Découpe des tubes de transfert + extensions |
10 days | Mon 27/11/00 | Fri 8/12/00 |
29 | VETO+Fibres optiques - Dép.+ échafaudages |
3 days | Tue 21/11/00 | Thu 23/11/00 |
30 | Compt. Pb 40° A + C |
3 days | Tue 21/11/00 | Thu 23/11/00 |
31 | LASERS A + C - Dép. |
2 days | Fri 24/11/00 | Mon 27/11/00 |
32 | STIC A - Dépose |
2 days | Mon 27/11/00 | Tue 28/11/00 |
33 | STIC C - Dépose + Réassemblage |
2 days | Tue 28/11/00 | Wed 29/11/00 |
34 | Retrait SCQs ( Déconnexion Ch à vide ) |
5 days | Mon 27/11/00 | Fri 1/12/00 |
35 | Couronnes LASER |
1 day | Wed 29/11/00 | Wed 29/11/00 |
36 | VERTEX |
2 days | Fri 1/12/00 | Mon 4/12/00 |
37 | remove FCA |
2 days | Tue 5/12/00 | Wed 6/12/00 |
38 | MUB Prepare electronics |
5 days | Mon 27/11/00 | Fri 1/12/00 |
39 | MUB remove peripheral chambers, preparation for outer chambers |
15 days | Mon 27/11/00 | Fri 15/12/00 |
40 | Barrel Tuyautries peripheriques ED |
5 days | Mon 18/12/00 | Fri 22/12/00 |
41 | Comptages A+ C / Déconnexion electrique / Mise en sécurité HALON |
2 days | Mon 4/12/00 | Tue 5/12/00 |
42 | Comptages B+ D / Déconnexion Mise en sécurité HALON |
2 days | Wed 6/12/00 | Thu 7/12/00 |
43 | Rétablir l'éclairage B + D |
2 days | Fri 8/12/00 | Mon 11/12/00 |
44 | Passerelle B4 / D3 |
5 days | Fri 8/12/00 | Thu 14/12/00 |
45 | Phase III |
41 days | Thu 7/12/00 | Thu 15/2/01 |
46 | move A+C > Garage + séparation S de Compt. |
7 days | Thu 7/12/00 | Fri 15/12/00 |
47 | Ch. à vide DELPHI - retrait |
3 days | Thu 7/12/00 | Mon 11/12/00 |
48 | remove ID |
2 days | Tue 12/12/00 | Wed 13/12/00 |
49 | Open TPC for inspection (option) |
17 days | Thu 14/12/00 | Fri 19/1/01 |
50 | Rétablir l'éclairage A + C |
2 days | Fri 8/12/00 | Wed 13/12/00 |
51 | Séparation B / BARREL |
12 days | Thu 7/12/00 | Fri 22/12/00 |
52 | Séparation End-Cap / salle de comptage |
3 days | Mon 11/12/00 | Wed 13/12/00 |
53 | Echafaudage Av + remove FRICH |
9 days | Tue 12/12/00 | Fri 22/12/00 |
54 | remove FCB |
2 days | Mon 8/1/01 | Tue 9/1/01 |
55 | remove FEMC |
27 days | Wed 10/1/01 | Thu 15/2/01 |
56 | MUB remove outer chambers (A+C) |
10 days | Mon 18/12/00 | Fri 12/1/01 |
57 | MUB remove outer chambers (A+C) |
5 days | Mon 22/1/01 | Fri 26/1/01 |
58 | remove B4,B3 |
10 days | Mon 8/1/01 | Fri 19/1/01 |
59 | Phase IV |
35 days | Mon 15/1/01 | Fri 2/3/01 |
60 | remove B2 (stockage) ,B1 |
10 days | Mon 29/1/01 | Fri 9/2/01 |
61 | remove TOF side C |
10 days | Mon 15/1/01 | Fri 26/1/01 |
62 | remove MUF A and C |
10 days | Mon 12/2/01 | Fri 23/2/01 |
63 | remove HOF A and C |
7 days | Mon 19/2/01 | Tue 27/2/01 |
64 | Chemin de câbles endcaps ( double auréole ) |
7 days | Thu 22/2/01 | Fri 2/3/01 |
65 | Tuyauteries Eau démin. Endcaps |
7 days | Thu 22/2/01 | Fri 2/3/01 |
66 | Phase V |
25 days | Mon 5/3/01 | Fri 6/4/01 |
67 | remove thin EC |
6 days | Mon 5/3/01 | Mon 12/3/01 |
68 | remove MUB inner chambers C |
10 days | Mon 5/3/01 | Fri 16/3/01 |
69 | tube streamer Ar |
4 days | Tue 13/3/01 | Fri 16/3/01 |
70 | remove thick EC |
15 days | Mon 19/3/01 | Fri 6/4/01 |
71 | demontage / presentation barrel |
25 days | Mon 5/3/01 | Fri 6/4/01 |
72 | Phase VI |
15 days | Mon 9/4/01 | Fri 27/4/01 |
73 | remove A3 and C3 |
5 days | Mon 9/4/01 | Fri 13/4/01 |
74 | remove C2, C1 |
5 days | Mon 16/4/01 | Fri 20/4/01 |
75 | remove A2-> storage |
3 days | Mon 23/4/01 | Wed 25/4/01 |
76 | remove A1 |
2 days | Thu 26/4/01 | Fri 27/4/01 |
77 | Phase VII |
20 days | Mon 30/4/01 | Fri 25/5/01 |
78 | move BARREL-> garage |
1 day | Mon 30/4/01 | Mon 30/4/01 |
79 | Evacuation du chemin de câbles central |
4 days | Tue 1/5/01 | Fri 4/5/01 |
80 | remove D3 |
5 days | Mon 7/5/01 | Fri 11/5/01 |
81 | put A2 and B3 on D2 |
10 days | Mon 14/5/01 | Fri 25/5/01 |