Dism_for_expo  (Status: 11 Jan 2001)

Project Start Date: Mon 6/11/00
Project Finish Date: Fri 25/5/01

Task_Data

ID Task_Name Duration Start_Date Finish_Date
1

Réaménagement UX 85

20 days Mon 25/9/00 Fri 20/10/00
2

Réaménagement SX 8 - Réduction de l'emprise ATELIER Démontage de l'expo DELPHI

20 days Mon 9/10/00 Fri 3/11/00
3

remove central electronics

10 days Mon 27/11/00 Fri 8/12/00
4

remove electronics B3, B2, B1

20 days Mon 11/12/00 Fri 19/1/01
5

remove electronics B3, B2, B1

20 days Mon 11/12/00 Fri 19/1/01
6

remove electronics C2, C1

50 days Mon 11/12/00 Fri 2/3/01
7

remove electronics A2, A1

50 days Mon 11/12/00 Fri 2/3/01
8

remove electronics D2, D1

50 days Mon 11/12/00 Fri 2/3/01
9

Prepare platform B4

20 days Mon 11/12/00 Fri 19/1/01
10

Prepare platform C3, A3

50 days Mon 11/12/00 Fri 2/3/01
11

Prepare platform D3

45 days Mon 18/12/00 Fri 2/3/01
12

Phase I

20 days Mon 6/11/00 Fri 1/12/00
13

GAZ / Détecteurs - Purge

15 days Mon 6/11/00 Fri 24/11/00
14

Bouchon PX / Gaine d'extraction

5 days Mon 27/11/00 Fri 1/12/00
15

VSAT+Câblage STIC Système de ventil.intérieur BARREL

2 days Thu 23/11/00 Fri 24/11/00
16

SMC 4 ch sup + 4 ch inf

2 days Thu 23/11/00 Fri 24/11/00
17

Arrêt du solénoïde

1 day Mon 6/11/00 Mon 6/11/00
18

SOLENOÏDE - Démagnétisation

5 days Mon 13/11/00 Fri 17/11/00
19

Phase II

25 days Mon 20/11/00 Fri 22/12/00
20

SOLENOÏDE - réchauffement

5 days Mon 20/11/00 Fri 24/11/00
21

Solénoïde / N2

1 day Fri 24/11/00 Fri 24/11/00
22

open blindage / endcaps

1 day Mon 20/11/00 Mon 20/11/00
23

Vidange circuits EM-EG-EDem-

2 days Mon 27/11/00 Tue 28/11/00
24

Dépose tuyauteries EM-EG-EDem / B4-D3

3 days Wed 29/11/00 Fri 1/12/00
25

Dépose des pompes à vide

3 days Tue 5/12/00 Thu 7/12/00
26

Chambres,câbles + équipements He

5 days Mon 4/12/00 Fri 8/12/00
27

Cannes CRYO-D3 (check with Klaus Barth)

2 days Mon 4/12/00 Tue 5/12/00
28

Découpe des tubes de transfert + extensions

10 days Mon 27/11/00 Fri 8/12/00
29

VETO+Fibres optiques - Dép.+ échafaudages

3 days Tue 21/11/00 Thu 23/11/00
30

Compt. Pb 40° A + C

3 days Tue 21/11/00 Thu 23/11/00
31

LASERS A + C - Dép.

2 days Fri 24/11/00 Mon 27/11/00
32

STIC A - Dépose

2 days Mon 27/11/00 Tue 28/11/00
33

STIC C - Dépose + Réassemblage

2 days Tue 28/11/00 Wed 29/11/00
34

Retrait SCQs ( Déconnexion Ch à vide )

5 days Mon 27/11/00 Fri 1/12/00
35

Couronnes LASER

1 day Wed 29/11/00 Wed 29/11/00
36

VERTEX

2 days Fri 1/12/00 Mon 4/12/00
37

remove FCA

2 days Tue 5/12/00 Wed 6/12/00
38

MUB Prepare electronics

5 days Mon 27/11/00 Fri 1/12/00
39

MUB remove peripheral chambers, preparation for outer chambers

15 days Mon 27/11/00 Fri 15/12/00
40

Barrel Tuyautries peripheriques ED

5 days Mon 18/12/00 Fri 22/12/00
41

Comptages A+ C / Déconnexion electrique / Mise en sécurité HALON

2 days Mon 4/12/00 Tue 5/12/00
42

Comptages B+ D / Déconnexion Mise en sécurité HALON

2 days Wed 6/12/00 Thu 7/12/00
43

Rétablir l'éclairage B + D

2 days Fri 8/12/00 Mon 11/12/00
44

Passerelle B4 / D3

5 days Fri 8/12/00 Thu 14/12/00
45

Phase III

41 days Thu 7/12/00 Thu 15/2/01
46

move A+C > Garage + séparation S de Compt.

7 days Thu 7/12/00 Fri 15/12/00
47

Ch. à vide DELPHI - retrait

3 days Thu 7/12/00 Mon 11/12/00
48

remove ID

2 days Tue 12/12/00 Wed 13/12/00
49

Open TPC for inspection (option)

17 days Thu 14/12/00 Fri 19/1/01
50

Rétablir l'éclairage A + C

2 days Fri 8/12/00 Wed 13/12/00
51

Séparation B / BARREL

12 days Thu 7/12/00 Fri 22/12/00
52

Séparation End-Cap / salle de comptage

3 days Mon 11/12/00 Wed 13/12/00
53

Echafaudage Av + remove FRICH

9 days Tue 12/12/00 Fri 22/12/00
54

remove FCB

2 days Mon 8/1/01 Tue 9/1/01
55

remove FEMC

27 days Wed 10/1/01 Thu 15/2/01
56

MUB remove outer chambers (A+C)

10 days Mon 18/12/00 Fri 12/1/01
57

MUB remove outer chambers (A+C)

5 days Mon 22/1/01 Fri 26/1/01
58

remove B4,B3

10 days Mon 8/1/01 Fri 19/1/01
59

Phase IV

35 days Mon 15/1/01 Fri 2/3/01
60

remove B2 (stockage) ,B1

10 days Mon 29/1/01 Fri 9/2/01
61

remove TOF side C

10 days Mon 15/1/01 Fri 26/1/01
62

remove MUF A and C

10 days Mon 12/2/01 Fri 23/2/01
63

remove HOF A and C

7 days Mon 19/2/01 Tue 27/2/01
64

Chemin de câbles endcaps ( double auréole )

7 days Thu 22/2/01 Fri 2/3/01
65

Tuyauteries Eau démin. Endcaps

7 days Thu 22/2/01 Fri 2/3/01
66

Phase V

25 days Mon 5/3/01 Fri 6/4/01
67

remove thin EC

6 days Mon 5/3/01 Mon 12/3/01
68

remove MUB inner chambers C

10 days Mon 5/3/01 Fri 16/3/01
69

tube streamer Ar

4 days Tue 13/3/01 Fri 16/3/01
70

remove thick EC

15 days Mon 19/3/01 Fri 6/4/01
71

demontage / presentation barrel

25 days Mon 5/3/01 Fri 6/4/01
72

Phase VI

15 days Mon 9/4/01 Fri 27/4/01
73

remove A3 and C3

5 days Mon 9/4/01 Fri 13/4/01
74

remove C2, C1

5 days Mon 16/4/01 Fri 20/4/01
75

remove A2-> storage

3 days Mon 23/4/01 Wed 25/4/01
76

remove A1

2 days Thu 26/4/01 Fri 27/4/01
77

Phase VII

20 days Mon 30/4/01 Fri 25/5/01
78

move BARREL-> garage

1 day Mon 30/4/01 Mon 30/4/01
79

Evacuation du chemin de câbles central

4 days Tue 1/5/01 Fri 4/5/01
80

remove D3

5 days Mon 7/5/01 Fri 11/5/01
81

put A2 and B3 on D2

10 days Mon 14/5/01 Fri 25/5/01